    CCI Baja California Sur III

    ACCIONA Industrial carried out the design, supply, construction and start-up of a 42-MW power generation plant.

    ACCIONA Industrial carried out the design, supply, construction and start-up of a 42-MW power generation plant, consisting of an internal combustion engine-generator fired by fuel oil, including a 230-kV substation and auxiliary connections, completed over a period of 27 months. 

    The plant includes a steam turbine that completes the thermal cycle by making use of hot exhaust gases to generate additional clean energy. More than 300 km of electrical cables have been installed, and 50,000 diametric inches of piping have been installed in different systems.

    General Information

    Location
    La Paz, Baja California Sur (Mexico)
    Client
    CFE
    Capacity
    42 MW
    Contract type
    Design, supply, construction, and commission
    Year construction ended
    2014

     

    Image Gallery

    discover other flagship projects

    Adriatic LNG Terminal Caisson

    Algeciras (Spain)

    Construction of a liquefied natural gas terminal at the Harbour Perimeter of Campamento (Algeciras), which was then tugged and installed in the north of the Adriatic Sea, off the coast of Venice (Italy).

    CT-TG Baja California II Phase 1

    Baja California (Mexico)

    This plant will cover peak and emergency demands in Baja California, and is the first of this kind of technology in the state.

    Move up